Six-storey commercial building under construction, one general contractor, delivery in 3 phases, and one technical room per floor.

Context

Context

Six-storey commercial building under construction, one general contractor, delivery in 3 phases, and one technical room per floor.

Challenges

Challenges identified

  • Structured cabling must be installed before the walls are closed
  • Coordination with electricians for pathways
  • Technical rooms need to be organized from the structural phase
  • Security systems and WiFi must be ready at handoff

Scope

What we delivered

  • Cat 6A cabling pulled through all suites before wall closure - Phase 1
  • Deployment of MikroTik routing, Omada switches, racks, and patch panels in the 6 technical rooms - Phase 2
  • Deployment of UniFi cameras, UniFi Access, and TP-Link Omada WiFi coordinated with final delivery - Phase 3
  • Complete documentation delivered to the general contractor and the owner

Outcome

Result

Full technology delivery aligned with the construction schedule. No delays caused by the systems, and clean documentation handed over at final delivery.

Systems used

MikroTik (router) · TP-Link Omada (WiFi and switches) · UniFi Cameras · UniFi Access

MikroTik (router)TP-Link Omada (WiFi and switches)UniFi CamerasUniFi Access

Request a quote

Are you building or renovating a property?

Let’s coordinate the systems now.